Indianola Solar Project Update!

PROGRESS:

Initial designs, layouts, electrical/technical engineering completed

IMU secured approvals from City Board of Adjustment

NEXT STEPS:

Finalize federal grant funding (P.A.C.E.) and USDA approvals (P.A.C.E. = Powering Affordable Clean Energy)

TIMELINE:

Completion on track for Q2 2025, Construction to start by the end of 2024.

CHALLENGES:

Unexpected delays in securing federal grant funding despite project eligibility

MOVING FORWARD:

We’re working diligently to overcome these delays and keep the project on schedule for completion in Q2 2025.

STAY TUNED FOR FURTHER UPDATES!