The initial work, including preparing the site, installing fencing for security, and clearing trees, is complete. The crews have installed about two-thirds of the foundational supports,the racking systems, and the solar panels. Underground electrical work is nearly finished.
Solar Update
Solar Project Update
1. What has been completed so far on the Solar Project?

2. What still needs to be done?
The remaining solar panels and racking systems still need to be installed.
Crews need to complete the electrical wiring and connect all the major equipment.
Once construction is complete, there will be a final round of inspections and testing before the project is ready to go online.
3. When do you anticipate being complete and ready to utilize?
The project is on track to be operational by mid-November.
4. Have there been any challenges during construction?
The hilly terrain and tree-clearing created some challenges with the initial site layout, and some equipment components needed to be replaced.
However, these are normal issues for a large project, and the construction teams have successfully adapted to keep the project on schedule.